Once the Phan Thiet – Dau Giay expressway comes into operation, it is expected to reduce travel time between Ho Chi Minh City and the central beach city of Phan Thiet from six to two hours.
The 99-kilometer Phan Thiet – Dau Giay expressway, which was constructed in September 2020, is set to be completed by April 30. The expressway has a total investment cost of VND12.5 trillion ($532.71 million). It is basically now completed, with laying asphalt and painting road markings the only two remaining tasks.
Signs have been set up. The expressway allows the maximum speed of 120 kph and requires a minimum speed of 60 kph. A section of the expressway crossing by rubber forests in Cam My District in Dong Nai Province has been laid with asphalt. A section of the expressway crossing by rubber forests in Cam My District in Dong Nai Province has been laid with asphalt.