PPC Chairman Le Tuan Phong inspects the project of renewing the coastal trunk road DT.719B

06/05/2022, 10:31

On the morning of May 5, Chairman of the Provincial People's Committee Le Tuan Phong made a field inspection on the project of renewing the coastal trunk road DT.719B, sectioned Phan Thiet-Ke Ga and Ham Kiem - Tien Thanh road. Attending the trip, there were Vice Chairman of the Provincial People's Committee Nguyen Van Phong, and representatives of a number of related departments, branches, and localities.

The renewal of the coastal trunk road DT.719B, under the Phan Thiet - Ke Ga section was approved by the Provincial People's Committee on June 18, 2020, covering a 25.61 km long, 28m wide roadbed. The width of the road surface is 16m, the median strip is 11m, and the width of the curb is 0.5m on each side. The road structure is asphalt-concrete on a crushed stone base. The construction period is expected to last 38 months from November 25, 2020, to January 25, 2024, according to the Project Management Board (PMU) for investment and construction of traffic works.

phong.jpg
At the event.

Meanwhile, Ham Kiem - Tien Thanh road project was approved by the Provincial People's Committee on June 19, 2020, with a route length of about 7.7km, a roadbed of 37m wide, and a road surface width of 16m. The road structure is asphalt-concrete on a crushed stone base. The time to conduct the contract is 720 days (from November 16, 2021, to October 31, 2023). The total withdrawal area is 34.7 ha and 94 files. Of which, Phan Thiet city has 9.7 ha, 30 files, and Ham Thuan Nam district has 25 ha, 64 files. Currently, all notices to the land acquisition have been completed with 94/94 files, reaching 100%. The construction unit has conducted organic excavation and handover of the site. Accumulated capital disbursement from the beginning of the project to now is 92,747 billion VND.

After checking the reality and listening to the reports at the meeting, the Chairman of the Provincial People's Committee Le Tuan Phong assessed that the relevant departments, branches, localities, and construction units have made great efforts. The overall progress of the compensation and site clearance work has progressed but is still very slow and has not completed the schedule required by the Provincial People's Committee. For the project of renewing the coastal trunk road, DT.719B under the Phan Thiet - Ke Ga section, the amount that has to pay for the remaining project-affected households is still very large (65%).

In order to speed up the site clearance and ensure the construction progress, Chairman Phong requested relevant departments, branches, localities, and construction units to focus on making more positive changes. Specifically, it should try to complete the entire routes of the project before April 30, 2023, according to the set schedule. Particularly the section from the beginning of National Highway 1A to the roundabout Ham Kiem - Tien Thanh (belonging to the project of renewing the coastal road DT.719B section Phan Thiet - Ke Ga) is expected to open on September 2, 2022.

As for the compensation for site clearance, the Provincial People's Committee requested the People's Committees of Phan Thiet City and Ham Thuan Nam district to focus on speeding up the progress, solve difficulties and problems, and organize payment and handing over the site to the construction unit as soon as possible.

TRANSLATED BY MỸ THIỆN

According to Bao Binh Thuan
Copy Link
Related articles
Efforts made to ensure best care for children with disabilities
Vietnam has made great efforts to care for about 700,000 children with disabilities, including measures to enhance the efficiency of policies supporting them.

(0) Comments
Focus
Do not miss
POWERED BY ONECMS - A PRODUCT OF NEKO
PPC Chairman Le Tuan Phong inspects the project of renewing the coastal trunk road DT.719B